Baseline: the snapshot of the plan that shows how far you have drifted

Also known as: Project baseline · schedule baseline

A baseline is the saved copy of a project’s approved plan, with its dates and durations. It lets you compare what was planned with what is actually happening at any time.

Why you need one

A live plan gets updated every week. If you only keep the current plan, you will never know how far it has moved: the delay disappears the moment someone changes the dates. The baseline is the reference nobody touches.

An example

Installing a packaging line is approved with a handover date of April 30, and in June it is still open. The baseline shows where the variance started: in the electrical work, which ran three weeks over. Not in commissioning, which is what everyone remembers.

When to change it

Only when the commitment changes: the customer expands the scope or agrees to a new date. Then you save a new baseline, and it is worth writing down why it changed.

The usual mistake

Resetting the baseline every time the project slips. That way the project is always “on schedule” and nobody learns anything. You change it because the agreement changed, not because reality did.

Keep reading

Related terms

Projects

Gantt chart

Project timeline · schedule chart

A Gantt chart is a project schedule drawn as bars: each task takes one row, and its bar starts and ends on its planned dates.

Projects

Task dependencies

Finish-to-start · predecessors

Task dependencies are the rules that tie the start or finish of one task to another, such as painting not starting until the plaster has dried.

Projects

Timesheet

Time entries · project time tracking

A timesheet is the record of the time each person spends on each project, task or customer, used to know what each job costs and what is billable.

On the blog

See all 53 glossary terms

Request a demo

Shall we look at it with your data?

We will show you how what you just read works in attendo, with your own assets, tickets and customers. If it is not a fit, we will tell you.

  • With your operation, not a generic demo
  • A real person from our team replies
  • No cold calls afterwards

Would you rather talk first?

Which area do you want to see in the demo?

With your work email we prepare the demo around your case.

In one or two sentences.

If you chose Maintenance (CMMS)

If you chose Field work (Field Service)

If you chose Facility Management

If you chose any other area

Only if you would rather we call you.

Data protection. Controller: AxisOne Group SL. Purpose: preparing the demo you request and replying to you. Legal basis: your consent and the request you make. Recipients: we do not disclose your data; Cloudflare (website) and Brevo (email notices and confirmation) process it on our behalf. Rights: access, rectification, erasure, objection, restriction and portability, at privacy@attendo.me. More information in the privacy policy.

What happens when you send it. Someone from our team reads what you tell us and writes to you to agree on a time for the demo. Our hours: Monday to Thursday 9:30 AM to 6:30 PM and Friday 9:30 AM to 2:30 PM, Spain time.